Low Graphics Version
  
Mon., Jan 5, 2009
Homepage > ... > Public Works > Engineering Divisions > Construction UpdateE-mail storyPrint friendly format
Construction Update

Street construction and/or road closures will be occurring at the following locations:


MAGNOLIA STREET IMPROVEMENTS FROM EDINGER TO I-405; TRASK STREET FROM BEACH BOULEVARD TO NEWLAND STREET; GOLDENWEST STREET FROM BOLSA AVENUE TO HAZARD AVENUE

Staff has incorporated and transmitted the final punch lists from the cities of Fountain Valley and Garden Grove this week. The contractor has ten working days to complete the final punch list. 

CITYWIDE STREET IMPROVEMENT PROJECT - OVERLAY 08-09

 
The contractor has completed the first coat of paint and will apply the second coat next week to complete the project.

Click here for a street list of affected streets

 

Click here for a street map of affected streets

 

CITY WIDE STREET IMPROVEMENTS – CDBG 08-09

 

The contractor will edge and grind tomorrow, November 21, and pave the beginning of next week. The contractor will then continue to raise manholes and valves for duration of one week.  

 The project includes the following streets:

·        Coronet Avenue from Oakcliff to Poinsettia.

·        Bevan Avenue from end (east of Poinsettia) to end.

·        Calendula Avenue from Dalewood Lane to Bushard Street.

·        Dalewood Lane from Calendula Avenue to Mc Fadden.

·        Oakcliff Drive from Mc Fadden to Coronet.

 

 

 

 

Updated 12-2-08

Top 
Copyright © 2000 - 2009 City of Westminster, CAPowered by