Street construction and/or road closures will be occurring at the following locations:
MAGNOLIA STREET IMPROVEMENTS FROM EDINGER TO I-405; TRASK STREET FROM BEACH BOULEVARD TO NEWLAND STREET; GOLDENWEST STREET FROM BOLSA AVENUE TO HAZARD AVENUE
Staff has incorporated and transmitted the final punch lists from the cities of Fountain Valley and Garden Grove this week. The contractor has ten working days to complete the final punch list.
CITYWIDE STREET IMPROVEMENT PROJECT - OVERLAY 08-09
The contractor has completed the first coat of paint and will apply the second coat next week to complete the project.
The contractor will edge and grind tomorrow, November 21, and pave the beginning of next week. The contractor will then continue to raise manholes and valves for duration of one week.
The project includes the following streets:
·Coronet Avenue from Oakcliff to Poinsettia.
·Bevan Avenue from end (east of Poinsettia) to end.
·Calendula Avenue from Dalewood Lane to Bushard Street.
·Dalewood Lane from Calendula Avenue to Mc Fadden.