Current City Construction Projects

(Updated April 2018)

Project: Westminster Boulevard from Newland Street to Magnolia Street Awarded to Hardy and Harper, Inc.

Start Date:  April 2018 Completion Date:July 2018

Project Manager: Theresa Tran - (714) 548-3464

Scope of Work: The work consists of removing and replacing (deep lift) deteriorated pavement areas, damaged concrete curb, gutter, cross-gutter, driveway approach, sidewalk, alley and alley apron; constructing wheel chair ramps, replacing broken traffic signal and water meter boxes, cold planning existing pavement areas, placing pavement reinforcing fabric, installing of new asphalt concrete pavement, adjusting storm drain, sewer manholes, and water valves to finished grade, installing traffic signal loops, striping, pavement markings, curb painting and signs, and all appurtenant work in connection therewith.

Night Work: Hardy & Harper, Inc. will start night construction beginning  Sunday night, April 22, 2018 to the morning of Wednesday, May 9, 2018. The work includes cold milling the existing asphalt pavement and installing new asphalt concrete overlay. There will be twelve (12) working nights altogether. The Contractor is only working five (5) nights per week (Sunday night to Thursday night).  There will be no night work on Friday and Saturday.The Contractor’s working hours will be from 9:00 pm to 5:00 am, Sunday through Thursday.  The Contractor will pass out night work notices to all residents and businesses along Westminster Blvd. City staff will watch closely and inspect the work for all those nights.